24/7 emergencies 814 777 6921812 230 6079WhatsApp 811 786 0768
Electrónica MonterreyElectrónica MonterreyLaboratorios Creativeit Talk to an engineer
Menu

Why does a bushing fail?

Bushings fail mainly because of moisture penetrating the insulation, partial discharges that erode it, overheated connections and external contamination, and the failure can be violent.

A component exposed to everything

A bushing combines high voltage, load current, temperature, moisture and contamination in a single element. Its main insulation is a paper-and-oil or resin structure with capacitive layers, and anything that degrades it alters the field distribution.

Failure mechanisms

  • Moisture: enters through deteriorated seals and gaskets, or through a leak. Water raises dielectric losses and promotes discharges.
  • Partial discharges: in voids or deteriorated layers, they erode the paper and produce gases and carbon. They progress to a failure between layers.
  • Thermal runaway: as dielectric losses rise, the temperature increases, which in turn raises the losses, until breakdown.
  • Heating at the connection: loose or oxidized terminals raise the temperature of the conductor and the bushing.
  • External contamination: salt, dust or dirt on the outer insulator cause surface leakage and discharges, and even flashover.
  • Test tap without cover or ground: on condenser bushings, this leaves a point at high voltage.
  • Overvoltages: lightning or switching impulses that damage layers.
  • Mechanical damage: impacts, stress from the conductors or earthquakes that crack the porcelain or seals.

Early signs

  1. An increase in tan delta or a change in capacitance relative to the history or to sister bushings.
  2. Low oil level or darkened oil, on models with a sight glass.
  3. Hot spots in thermography.
  4. Discharge noise or corona visible in ultraviolet.
  5. Gases in the bushing oil, if it is sampled.

Why it is watched so closely

A failure in the main insulation of a bushing can release a great deal of energy, shatter the porcelain and cause a transformer fire. That is why it is subject to periodic capacitance and tan delta measurements, and each one is compared with the nameplate and with its sister bushings.

What to check first

External condition, level, test tap cover and the trend of the electrical measurements. A sustained change deserves investigation before it turns into a failure.

Warning: work near bushings and measurements on them involve high voltage. They must be carried out by qualified personnel, in accordance with the applicable regulations.