What is being checked
That the transformer’s internal connection and phase displacement match those on the nameplate and what the installation requires. This is important after transport, a repair or a rewind, or before connecting in parallel.
Reduced-voltage method
- With the transformer de-energized and isolated, the high-voltage winding is supplied with a reduced three-phase voltage of known phase sequence.
- A high-voltage terminal is bonded to the corresponding low-voltage terminal, so that both are at the same potential.
- The voltages between the remaining high-voltage and low-voltage terminals are measured.
- The phasor diagram is drawn from those measurements: the relationship between the measured voltages is characteristic of each group and its phase displacement.
The method relies on the fact that, when two terminals are bonded, the phasors of both sides share a common origin, and the distances between the other vertices correspond to the measured voltages. The matches between certain readings, and the differences between others, make it possible to tell one group from another.
Ratio meter method
Many turns ratio instruments apply a reduced signal to each phase and measure phase angle and polarity as well as ratio. In this way they identify the group directly and detect wrong connections, such as crossed phases or reversed windings. It is the most common method when the equipment is available.
What to compare
- The measured group against the nameplate and the manufacturer’s diagram.
- The phase sequence of the supply: a reversed sequence changes the apparent angle.
- The voltage ratio per phase, which must be consistent across all three.
What to check first
Confirm the phase sequence, the terminal markings and that the neutral is correctly identified. A marking error on a bushing looks like a transformer error. If the result does not match the nameplate, check the external connections before suspecting the internal connection.
Reduced voltage is used for safety and to avoid saturating the core. This work is carried out by qualified personnel with the equipment de-energized and disconnected from the network.