What it is for
Commissioning is the last chance to find assembly errors before the plant goes into operation. A polarity error, a badly crimped connector or a string one module short are easy to detect at the outset and costly later on. The verification also establishes a starting point for comparing future performance.
Verification stages
- Document review: drawings, equipment list, schematics and protection settings match what was installed.
- Visual inspection: modules undamaged, structure firm, wiring secured and protected, connectors complete, labels, grounding.
- String electrical tests: polarity, open-circuit voltage and current, compared between similar strings.
- Insulation resistance and continuity of grounds and conductors.
- I-V curves of strings, with irradiance and cell temperature logged, to check against what is expected.
- Protection and tripping: operation of disconnect switches, fuses and surge protection.
- Energization and inverter startup, verifying alarms, synchronization and grid parameters.
- Performance test: compare power and energy with what is expected under the measured irradiance.
What an engineer sees in practice
The open-circuit voltage of identical strings should be very similar; a string that differs suggests a missing module, an open connector or damaged diodes. Comparison between strings, more than the absolute value, is the fastest tool.
How to interpret the result
Values are recorded and filed as a baseline. Any finding is corrected and the affected test is repeated. Acceptance criteria and the content of reports depend on the contract and the applicable regulations, and it is advisable to define them before starting.
A solar array maintains dangerous voltage as long as there is light. Tests and switching operations must be carried out by qualified, authorized personnel, following the applicable safety regulations.