What is to be demonstrated
The grid requires that connected generation neither endanger people nor degrade the supply to other users. Verification confirms that the system disconnects when it should, that it does not inject unacceptable disturbances, and that the installation matches what was submitted to the grid operator.
Items reviewed
- Voltage and frequency protections: configured trip thresholds and times compared with those required.
- Anti-islanding protection: the inverter must stop injecting if the grid is lost.
- Reconnection: the inverter must wait for the grid to stabilize before injecting again.
- Quality of the injected power, such as harmonic distortion, DC component and fluctuations.
- Behavior during voltage sags and reactive power control, where required.
- Metering, disconnecting means and signage, and grounding.
How it is verified
Part of the verification is documentary: equipment certificates, single-line diagrams and settings. Another part is practical: disconnection is tested by simulating grid conditions, measurements are taken with a power quality analyzer during operation, and the results are compared against the applicable limits. Local regulations, which include the Código de Red (grid code) and the operator’s requirements, define what is required and how.
What an engineer sees in the field
The most common nonconformities are protection settings different from those required, equipment without the requested certification, differences between the diagram submitted and what was installed, and distortion measurements that exceed limits because of the combination with other loads.
Notice
Tests on energized installations and at the point of connection are the responsibility of qualified personnel following the applicable electrical safety regulations and the grid operator’s procedures.