What it is
Motors, transformers and reactors need a magnetic field to operate. Creating that field means storing energy in each half-cycle and returning it in the next. This energy exchange produces a current that is out of phase with the voltage: reactive power (Q, in var) measures that exchange. Together with active power (P, in W) it forms apparent power (S, in VA) through the relationship S² = P² + Q² for linear loads.
Why it is a problem
Although reactive power does no work, the current that accompanies it flows through conductors, transformers and generators. That additional current causes:
- Losses in the conductors, which depend on the square of the current.
- Greater voltage drop on the line.
- Use of the kVA capacity of transformers and cables, which is then no longer available for useful active power.
In addition, many tariff schemes penalize a low power factor, although the specific rules depend on each regulation.
How it is compensated
A capacitor supplies reactive power of the opposite sign to that of an inductive load. If it is installed near the load, the reactive power circulates locally between the capacitor and the load, and the network supplies only the active power and the remainder. Current at the service entrance falls, power factor rises and upstream losses are reduced. Compensation can be individual at the motor, by group or centralized at the main switchboard.
What an engineer sees in practice
An analyzer shows active, reactive and apparent power, together with the power factor. After compensation, line current decreases for the same active power. If overcompensated, however, the current rises again with a capacitive character and the voltage at the installation point can increase.
What to check before compensating
The harmonic content of the facility must be checked, because capacitors interact with the network inductance and can produce resonance. How the load varies during the day must also be considered: fixed compensation that is oversized at low load causes overcompensation. Installing and connecting capacitor banks is work for qualified personnel.