What is a fault tree?

A fault tree is a logic diagram that starts from an undesired event and breaks down, using AND and OR gates, the combinations of failures that can produce it.

Top-down reasoning

A fault tree starts with the top event, an undesired occurrence such as “the pump does not deliver flow”. From there it asks what must happen to produce that event and breaks it down into simpler events, until it reaches basic causes that are not subdivided further.

Logic gates

Gate Meaning
OR The event occurs if any of the inputs occurs.
AND The event occurs only if all the inputs occur at the same time.

AND gates reflect redundancy: all the redundant elements must fail. OR gates reflect single points of failure.

How it is built

  1. Define the top event and the system boundaries precisely.
  2. Identify the immediate events that cause it and connect them with the correct gate.
  3. Repeat the process level by level until reaching basic events.
  4. Check that each gate describes necessary and sufficient causes, not an informal list.

What the tree yields

Qualitative analysis identifies the minimal cut sets: the smallest combinations of basic events that are enough to produce the top event. Sets made up of a single event reveal single points of failure. If the probabilities of the basic events are known, the probability of the top event can also be estimated.

When it is worth using

It is useful for investigating a failure that has already occurred or for evaluating a system with redundancies and protections. It differs from failure mode and effects analysis, which starts from components and moves toward the consequences: the tree goes from the consequence to the causes. It is not practical when the system is huge and poorly bounded.