What it defines
The neutral grounding scheme, or system grounding arrangement, establishes two things: how the transformer or generator neutral relates to ground, and how the exposed metal parts of equipment are connected to ground. These decisions determine how much current flows during an insulation fault, what touch voltages appear, and which device must open.
How to read the letters
The first letter indicates the situation of the source relative to ground: T if the neutral is connected directly to ground, I if it is isolated or connected through an impedance. The second indicates the situation of the installation’s exposed metal parts: T if they have their own ground, N if they are connected to the system neutral.
- TN: grounded source and exposed parts bonded to the neutral. A phase-to-frame fault becomes a high-current short circuit that trips the overcurrent protection. It is subdivided according to whether the neutral and protective conductor are separate (TN-S), combined (TN-C), or partly combined (TN-C-S).
- TT: grounded source and exposed parts with an independent ground. The fault current returns through the earth and is limited, so residual-current devices are usually employed.
- IT: source isolated or grounded through an impedance. A first fault produces a small current and allows operation to continue while it is located, and it is monitored with an insulation monitor. A second fault on another phase behaves like a short circuit.
Why the choice matters
A scheme that limits fault current favors continuity of service and reduces arc damage, but makes the fault harder to detect with ordinary protections. One that allows high current simplifies detection but can cause more damage and voltage drops. In medium-voltage industrial networks, the choice also includes a solidly grounded, resistance-grounded, reactance-grounded, or isolated neutral.
How to identify the scheme in the field
The source’s ground connection point, the presence of separate neutral and protective conductors, and fault loop impedance measurements are inspected. The applicable standards set the requirements for each scheme. These checks involve electrical risk and are done by qualified personnel.