What the verification looks for
A cable leaves the factory tested, but shipping, pulling and the installation of splices and terminations can damage it. Pre-commissioning verification aims to find that damage while repair is still inexpensive and no load is connected.
Typical stages
- Visual inspection: condition of the reels, sealed ends, signs of impact or crushing, and whether bending radii were respected during pulling.
- Document check: confirm that the cable, its accessories and the configuration match the project.
- Outer jacket test: a DC voltage is applied between the metallic shield and ground to detect jacket damage caused during installation, which would let moisture in.
- Insulation resistance of each conductor to shield and ground, as a baseline check.
- Continuity and phase sequence: confirm that each conductor connects the correct points at both ends and in the intended order.
- Shield and ground check: correct connection of the metallic shields according to the grounding scheme.
- Withstand test: application of a high stress defined by the specification or the standard, with a source suited to the type of insulation. In many cases it is complemented by a partial discharge measurement.
How to interpret the result
The results of this first verification are kept as a baseline. Any later maintenance measurement is compared against it. A weak value in a jacket test, even if it does not prevent operation, warns of damage that may allow water to enter.
What to check first if there is a failure
The cause is almost always in the accessories, not in the cable. Check splices and terminations before suspecting the continuous run.
These activities involve hazardous voltages: they must be carried out by qualified, authorized personnel, following the applicable regulations and the facility’s lockout and grounding procedures.