How is an Ishikawa diagram used for an electrical failure?

An Ishikawa diagram organizes the possible causes of an electrical failure into categories, like a fish skeleton, so they can be reviewed systematically instead of settling for the first idea.

What it is

The Ishikawa, or fishbone, diagram places the effect (the failure) at the head and the possible causes on branches grouped by category. It does not identify the cause, but it ensures that all areas are considered before deciding what to test.

How to draw it

  1. Write the problem precisely at the head: “the thermal-magnetic circuit breaker trips when the compressor starts.”
  2. Choose categories suited to the case.
  3. Brainstorm as a team: add possible causes under each category and go deeper with sub-causes.
  4. Mark the most plausible causes based on the data.
  5. Design a test for each one and record the result.

Useful categories for electrical failures

Category Examples of possible causes
Power supply Voltage drop, phase imbalance, harmonics, transients.
Equipment Deteriorated insulation, degraded component, incorrect setting.
Connections Loose terminals, heating, corrosion, undersized conductor gauge.
Environment Humidity, dust, temperature, vibration.
Operation Overload, frequent starts, use outside specification.
Maintenance Previous interventions, non-equivalent spare parts, lack of inspection.

What an engineer sees in practice

The value of the diagram appears when ideas are checked against measurements. One branch can be ruled out with a simple voltage reading; another requires hours of logging. The diagram serves as a shared checklist so that the team does not repeat tests.

When it is not enough

It is an organizing tool, not a quantitative analysis tool. It does not show the logical relationships between causes or their probability; a fault tree is used for that. And if the diagram fills up with opinions without data, it only hides ignorance.

Measurement work on energized installations must be carried out by qualified personnel in accordance with applicable regulations.