How is a grid-tied PV system sized?

A grid-tied PV system is sized starting from consumption and available area, estimating the energy per installed kilowatt according to the solar resource, and verifying that strings, inverter and protection devices are compatible.

The logical order

Sizing does not start with the modules but with the question of what is to be covered. A grid-tied system does not need batteries: it supplies energy to the site’s electrical network and relies on that network when there is no sun. That is why the starting point is the energy consumed, not the peak power demanded.

Calculation steps

  1. Consumption: energy consumed over a representative period, looking at seasonal variation and the usage profile.
  2. Solar resource: the plane-of-array irradiation available, which depends on location, tilt and orientation.
  3. System losses: temperature, soiling, shading, wiring, mismatch, inverter and degradation, summed up in a performance ratio.
  4. Required power: target energy divided by the energy each installed kilowatt produces, given the losses.
  5. Constraints: available area, structure, budget, and limits set by interconnection regulations or the capacity of the service entrance.

Equipment selection and compatibility

With the power defined, modules and an inverter are chosen. The ratio of installed DC power to the inverter’s AC power is a design decision: some oversizing of the array is common, because the system rarely operates at rated power. The string is then verified: the number of modules in series must keep the voltage within the inverter’s operating window in both cold and heat, without exceeding its maximum input voltage, and the current must be compatible with its input.

Protection and connection

Conductors, overcurrent and surge protection, disconnecting means and grounding are sized according to the applicable electrical regulations. Interconnection with the grid depends on the utility’s requirements and local regulation.

What an engineer sees in practice

A design is a balance between production, space, cost and tolerance to shading. An energy estimate that does not consider the site’s actual shading usually turns out optimistic, and verification of voltages on the coldest day is the design error seen most often.

Design and installation must be carried out by qualified personnel, following current electrical regulations.