How Is a Transformer Prepared for Out-of-Service Electrical Testing?

For out-of-service electrical testing, the transformer is de-energized, isolated from all its sources and loads, verified free of voltage and grounded, and the external connections to its bushings are removed, in addition to recording conditions and reference data.

Safety before measurement

Preparation begins with de-energization and the libranza: opening all supply and return points, lockout and tagout, verification of absence of voltage, and grounding. A transformer can remain energized through backfeed from loads, voltages induced by nearby lines, and residual charge in the insulation after certain tests. The work is performed by qualified personnel in accordance with current regulations.

Isolating the test object

  • Disconnect busbars, cables and conductors from the bushings. If they remain connected, the test also measures those elements and the result does not represent the transformer.
  • Disconnect or isolate surge arresters, voltage transformers and other devices connected to the bushings or the neutral.
  • Remove or open the neutral-to-ground connection when the method requires it.
  • Ground the tank, and the terminals not under test, according to the procedure for each test.

Surface and ambient conditions

Moisture and dirt on the bushing porcelain create leakage paths that alter insulation measurements. The surfaces are cleaned and dried. Oil and ambient temperature and humidity are recorded, because insulation results depend on them, and if the transformer was recently shut down, you wait for it to stabilize thermally.

Reference information

  • Nameplate data, tap changer position and oil level.
  • Previous test and factory reports, for comparison.
  • History of events such as through-faults, protection trips or moves.
  • Condition of accessories, such as gas and pressure relays.

Suggested test order

Tests sensitive to residual magnetism, such as excitation current and frequency response, are done before injecting direct current. The ratio, winding resistance and insulation measurements are then performed, and results, instruments and conditions are recorded. When finished, the insulation is discharged, the test leads are removed, the connections and grounds are restored, and the libranza is returned.

A defined order prevents tests from contaminating the ones that follow and makes it possible to compare results between campaigns.