How Is a Transfer Between the Normal Source and an Emergency Generator Planned?

A transfer between the normal source and an emergency generator is planned by defining which loads to back up, how the changeover will be made without backfeeding the utility, how the generator starts and picks up load, and how the protection is coordinated.

What to decide first

Planning begins with the scope: which loads must be backed up and how urgently. They are usually separated into those vital to people’s safety, those critical to the process, and those that can be dispensed with. That classification defines the size of the generator and the transfer scheme.

Type of transition

  • Open transition: the switch disconnects one source before connecting the other. There is a brief interruption, but the two sources are never connected in parallel.
  • Closed transition: the sources are connected in parallel for an instant, which avoids interruptions in planned transfers. It requires synchronism, additional protection and authorization from the utility.

In both cases, the mechanical or electrical interlock must prevent the generator from feeding the utility system by mistake: backfeed endangers those working on the de-energized network.

Generator sizing and behavior

A generator has much less fault current capacity than the utility, and its voltage drops further when large motors start. That is why load steps, the starting sequence and nonlinear loads are studied, such as drives and uninterruptible power supplies, which distort its voltage more than they distort the utility’s. Protection coordination must be reviewed with the generator’s fault current, which may not be enough to trip the devices as intended.

Grounding and neutrals

You must define whether the transfer switches the neutral (additional poles) or the neutral is common. An incorrect choice produces unintended ground-fault current paths and improper operation of the ground-fault protection.

Sequence and time delays

  • Detection of normal source failure and a delay to avoid starts on brief voltage sags.
  • Starting, stabilization and closing onto the generator.
  • Return to the utility with a delay, so that the utility voltage is stable.
  • Generator cooldown time after the return.

During retransfer, motors that are still spinning have residual voltage; switching without considering their phase can cause overcurrents and mechanical stress. Time delays or phase monitors are used.

Common mistakes

  • Sizing the generator only by the sum of the powers, ignoring motor starting.
  • Skipping tests under real load.
  • Not coordinating protection with the generator’s fault current.
  • Assuming the neutral will take care of itself.

Switching and testing are carried out by qualified personnel in accordance with applicable regulations.