How Is a Transformer Winding Resistance Test Performed?

The winding resistance test injects direct current into each winding and measures the voltage drop to calculate its resistance, which makes it possible to detect loose connections, broken strands and tap changer problems.

Basis

The resistance of a copper or aluminum winding is very small, so it is measured by the four-terminal method: two conductors inject the current and two separate ones measure the voltage at the winding terminals. This excludes the resistance of the test leads and clamps. The resistance is the voltage divided by the current.

What to keep in mind when measuring

  • Stabilization: the winding is a large inductance. When current is applied, the reading takes time to stabilize, according to the ratio of inductance to resistance. High-power, low-resistance windings need more time.
  • Stored energy: when the current is interrupted, the accumulated magnetic energy is released and can generate a high voltage. The instrument must provide controlled discharge, and the leads are not disconnected until it has finished.
  • Temperature: resistance depends on the conductor temperature. The winding temperature, which is slower to establish than the oil temperature, is recorded, and the value is corrected to a reference temperature for comparison.
  • Tap changer: it is measured at each position, and on load tap changers the measurement is repeated while running through the range, since this reveals worn contacts or discontinuities in the transition.

Connections

Measurement is made phase by phase on a wye with an accessible neutral, and between pairs of terminals on a delta, in which case the value combines two phases in parallel with the third. The procedure and the calculation of the per-phase resistance depend on the connection.

Common mistakes

  • Reading before the value stabilizes.
  • Comparing values at different temperatures without correcting them.
  • Using dirty or poorly tightened clamps, which add resistance.
  • Disconnecting with the winding charged.

How to interpret the result

The three phases are compared with one another, the values are compared with factory values or those of previous tests, and the behavior at each tap changer position is reviewed. A higher-than-expected resistance in one phase suggests a poor connection, broken strands or a faulty tap changer contact. A lower one may be due to shorted turns, although other tests confirm this better.

After direct current is injected, the core may remain magnetized; tests sensitive to this are done first, or the core is demagnetized. These tests are performed by qualified personnel with the transformer de-energized.