Prepare before arriving
Substation switching is an ordered sequence of actions on high-energy equipment. Errors usually come from a lack of clarity: who authorizes, in what order and with the system in what state. Preparation aims to ensure that each person knows what they will do and what the others will do.
Elements of preparation
- Roles and authority: one person responsible for the work, another in charge of switching, support staff, and a liaison with system operations. Everyone knows who gives the orders and who can stop the work.
- Procedure and diagrams: the sequence for opening, isolating, verifying the absence of voltage and grounding is reviewed, along with the restoration sequence. Diagrams must reflect the actual state.
- Risk analysis: site hazards, such as induced voltage, step voltage, weather, nearby energized equipment and switching under load.
- Qualification and authorization: each person is cleared for their task.
- Equipment and tools: hot sticks, detectors, temporary grounds, PPE, signage and barriers, all inspected and with current test records.
- Communication: defined means, repeat-back of orders, and confirmation of each step before it is carried out.
- Emergency plan: routes, location of the first aid kit and defibrillator, contact with emergency services, and who cuts the power.
On-site pre-job briefing
Before starting, the crew goes over the sequence, marks out the zones, confirms the state of the equipment, shares the risks and clarifies which conditions require stopping work. Everyone is asked to voice any doubts.
What the engineer sees in practice
- Orders repeated aloud and confirmed, with no improvising.
- A single person directing the switching.
- Records of each step, with the time and the person responsible.
- Lockouts and grounds placed before anyone approaches the equipment.
Closing out the work
When the work is finished, grounds and lockouts are removed in the reverse of the planned order, the area is checked to confirm no people or tools remain, and operations is informed before re-energizing.
Substation switching is high-risk and must be done by qualified personnel, following the applicable regulations.