Structure of the bridge
It is an AC bridge with four arms. The first contains the object being measured, represented as a capacitance with a series resistance for the losses. The second contains a very low-loss standard capacitor, often with compressed gas as the dielectric. The third is a resistor, and the fourth a resistor in parallel with a capacitor. A null detector is connected between the two midpoints.
How the result is obtained
The variable resistor and capacitor are adjusted until the detector indicates a null signal. At that balance point, the two branches divide the voltage in the same way and simple relationships hold:
- The capacitance of the object is proportional to the standard capacitance multiplied by the ratio of the arm resistances.
- The dissipation factor is proportional to the angular frequency and to the resistance and capacitance of the adjustable arm.
A change in the insulation thus translates into a readjustment of the balance.
Why it suits insulation measurements
The standard capacitor withstands high voltage without appreciable losses, so the object can be measured at elevated voltage. The elements of the low-voltage arm remain close to ground potential, which protects the operator. Because the dissipation factor of insulation is small, the method makes it possible to resolve very fine variations.
What to watch for in the measurement
- Shielding: stray capacitances to ground unbalance the bridge. Shields are used and, in classic versions, an auxiliary compensation circuit known as a Wagner circuit.
- Interference: nearby fields at frequencies close to the line frequency can mask the balance signal.
- Connection of the object: the connection configuration changes depending on whether or not one of the electrodes is grounded.
How to interpret the result
Today many digital instruments replace manual balancing, but the principle is the same. The values are compared with previous measurements on the same equipment and with the applicable criterion.
These activities involve hazardous voltages: they must be carried out by qualified, authorized personnel, following the applicable regulations and the facility’s lockout and grounding procedures.