How a pressure vessel is tested before operation

It undergoes a pressure test, normally hydrostatic, under an approved procedure, with inspection for leaks and deformation and recording of the results. The test must be done by qualified personnel in accordance with the design code.

Why it is tested

The pressure test demonstrates that the vessel as built withstands the pressure with margin and that its joints and seals do not leak. It is done before the equipment is placed in service, and again after major repairs or modifications, according to the design code and applicable regulations.

Why water is usually used

A liquid is practically incompressible, so it stores little energy. If something fails, the energy release is much smaller than with a compressed gas, whose expansion can be violent. That is why the hydrostatic test is the usual option; the pneumatic test is reserved for special cases and demands far greater precautions.

General sequence

  1. Preparation: review design and fabrication documentation, clean, isolate or remove devices that must not be tested, such as safety valves or sensitive instruments, and install plugs and blind flanges.
  2. Filling and venting: fill with the appropriate fluid and remove air at the high points, because trapped air compresses and distorts the reading.
  3. Instrumentation: use calibrated pressure gauges with a suitable range, plus an independent check gauge.
  4. Gradual pressurization: raise the pressure in stages, with pauses for inspection.
  5. Hold: maintain the test pressure for the time stated in the procedure, allowing the temperature to stabilize.
  6. Inspection: visually examine joints, welds and seals at the pressure defined by the code, looking for leaks or deformation.
  7. Controlled depressurization, draining and drying.

What the engineer sees

A rise in fluid temperature can raise the pressure in a closed system, and a drop during the hold can be thermal or due to a leak. That is why temperature is recorded along with pressure.

Safety

Pressure tests carry a risk of sudden energy release. They must be planned and carried out by qualified personnel, with an exclusion zone, following the code and the applicable safety standards. This guide is explanatory and does not replace the approved procedure.