How is the electrical installation for chargers sized?

The installation for chargers is sized from the power and voltage of each charger, treating the load as continuous, with suitable conductors, protective devices and transformer, and considering load management when there are several units.

Start with the current

The first data are the charger power and the supply voltage. In single-phase, the current is P divided by (V times power factor); in three-phase, it is P divided by (square root of three times line V times power factor). An AC charger actually limits the current it delivers to the vehicle, so sizing is based on the maximum current of the station, not that of the slowest vehicle.

Vehicle charging is a continuous load

A vehicle can charge at close to maximum current for hours. Conductors and protective devices are selected using the criterion that the applicable regulations set for continuous loads, which adds a margin over the rated current. Sizing to the rated current alone leads to sustained heating of cables, terminal blocks and protective devices.

Items to verify

  • Conductors: ampacity according to the installation method and ambient temperature.
  • Voltage drop: on long runs to the charger, it can dictate the conductor size even if the ampacity is sufficient.
  • Protective devices: thermal-magnetic circuit breaker and residual-current protection; many chargers integrate DC leakage detection, and this determines the type of upstream device.
  • Short-circuit capacity of the panel and the protective devices.
  • Grounding system and its resistance, because the connected vehicle is referenced to it.

Several chargers

With several units, the power of all of them is not always added up. A demand factor is applied and, if the system has load management, the total power is limited so that the transformer and the service entrance are not overloaded. It must be confirmed that the management works and what happens if communication is lost.

What to check first

Before installing, it is advisable to measure the building’s actual demand and the available capacity, because the most frequent cause of trips is a service entrance that was already close to its limit. Design and execution are the responsibility of qualified personnel, in accordance with the electrical installation regulations in force.