What needs to be confirmed
That the installation was built according to the design and the regulations, that it protects people in the event of a fault, and that the station communicates and delivers energy correctly. This is done first with the equipment de-energized and then energized, in that order.
Usual sequence
- Visual inspection: conductors, raceways, panels, identification, equipment mounting, condition of the cable and connector.
- Continuity of the ground connection and of the protective conductors.
- Insulation resistance between conductors and to ground, with the equipment disconnected from anything that could be damaged.
- Verification of the supply voltage, phase sequence and polarity on energizing.
- Checking the protective devices, including residual-current devices, and that they trip as expected; AC stations also commonly require detection of DC leakage currents.
- Functional test with a vehicle simulator that reproduces the connection states, a ground fault or a connector that comes unlatched, confirming that the station cuts off the energy.
- Review of communication with the management system, the emergency stop, the signage and the metering records.
What an engineer sees in the field
Common problems are poor ground connections, panels without adequate protection, a maximum current setting that differs from the actual capacity of the circuit, and communication failures with the central system. Testing the station under real load, in addition to the simulator, detects heating at terminals.
How to interpret the result
Commissioning ends with a record of measurements, settings and functional tests that serves as a baseline for later maintenance. A measurement that deviates from what is expected is resolved before energizing, not after.