How is a transformer’s sampling interval determined?

A transformer's sampling interval is set according to its importance, load, age, gas history and the trend of the results: the faster the indicators change or the more critical the equipment, the shorter it must be.

There is no single interval

A fixed schedule for all equipment is convenient but inefficient: it spends resources on stable transformers and comes too late for those that are changing. The interval is decided by the combination of risk and observed behavior.

Factors that define it

  • Criticality: the cost of a failure to the process or the supply justifies closer monitoring.
  • Type and size of the equipment: power units, transmission units or units with on-load tap changers require different attention from distribution units.
  • Age and condition of the oil and paper.
  • Load and operating temperature, especially if there are frequent overloads.
  • Gas history: concentrations and generation rate.
  • Environment: extreme dust, humidity and temperature.

The trend rules

After a baseline sample when the equipment enters service, stable results allow a long interval to be kept. If any gas increases, the interval is shortened until it is confirmed whether generation continues, stabilizes or accelerates. It is the change between samples, not just the value, that justifies the decision.

Events that call for an additional sample

  1. Protection trip or gas relay alarm.
  2. Nearby short circuit or through-fault.
  3. Severe overload or overheating.
  4. Repair, treatment or oil change, to establish a new baseline.
  5. Relocation or receipt of a unit.

What to check first when setting the plan

Review the available history, the importance of the equipment and the criteria of the standard or maintenance guide your organization adopts. It is advisable to review the plan periodically and adjust it when the data justify it. Sampling work is done with the equipment in safe conditions and by qualified personnel.