How is load estimated during an inspection?

Load during an inspection is estimated by measuring the current flowing at the time of the shot or by reading the panel instruments, and comparing it with the rated current of the circuit.

Why load is essential data

The heat generated by a defective connection is proportional to its resistance and to the square of the current. Without knowing how much current was flowing at the time of the shot, a temperature cannot be interpreted: modest heating at low load could become serious at full load.

How it is obtained

  • Fixed panel instruments: ammeters, analyzers or monitoring systems that already record the current.
  • Clamp meter: direct measurement on the circuit conductor, by qualified personnel. The measurement must be made on each phase.
  • Facility data: power consumed or load history, useful when there is no direct access.
  • Estimate from the process: on a motor, the current is compared with the nameplate current and with the state of the mechanical load.

How it is expressed

The usual reference is the percentage of the rated current of the circuit or of the capacity of the component under study. It is also important to record the load on each phase, since a difference between phases may be the origin of the anomaly.

How to interpret the result

  1. Record the load at the exact moment of each shot, since it can vary during the route.
  2. Consider the stabilization time: a load that has just risen has not brought the component to its steady-state temperature.
  3. To project heating to another load, the relationship with the square of the current is used as an approximation. It is a guide, not an exact measure, because resistance changes with temperature and cooling is not linear.
  4. At very low load, state in the report that the inspection is not conclusive.

When it does not apply

Extrapolation to full load does not replace a new inspection under representative conditions. Measuring current on energized equipment must be done only by qualified personnel, with the protective equipment and applicable regulations.