The principle
The measured temperature is not the severity. The same temperature rise can be tolerable in a low-criticality component and urgent in another. The classification assigns a priority level based on several factors.
Factors evaluated
- Temperature difference: from a similar component (for example, another phase) or from ambient. The former is better at eliminating the influence of the surroundings.
- Absolute temperature: compared with the limit of the material, the insulation or the component manufacturer.
- Load during measurement: resistive heating increases with the square of the current, so an anomaly seen at low load can be much more serious at full load.
- Trend: an anomaly that grows between inspections is more worrying than a stable one.
- Criticality and consequences: what happens if it fails, including fire risk, process shutdown or damage to other equipment.
- Measurement reliability: emissivity, reflections and distance that could distort the value.
How this translates into levels
Procedures usually define a few priority levels: follow-up at the next inspection, scheduled correction within a reasonable period, and immediate attention. The numerical thresholds separating the levels are defined by each standard, customer procedure or manufacturer criterion, and should be consulted in their current edition.
An example
Two connections show the same rise. The first feeds a lighting circuit that is lightly loaded at the time; the second, a critical motor that was running at half load. Although the figures are the same, the second receives a higher priority because of its criticality and the load margin not yet seen.
How to interpret the result
Document the factors that support the assigned level, not just the level, so that another person can review the decision. Corrective work on electrical equipment must be done by qualified personnel in accordance with applicable regulations.