Why an external fault can damage it
A fault outside the transformer, such as a short circuit on a line or bus, drives short-circuit current through its windings. That current produces mechanical forces proportional to the square of the current, along with rapid heating. If the windings or the insulation were already weakened, they can deform even though the fault was external.
Step 1: gather information
- Which protections operated: overcurrent, differential, gas, pressure or others. If an internal protection operated, the suspicion of damage rises.
- Relay records and oscillography: magnitude and duration of the fault current, type of fault and number of events.
- History: whether the unit had already been through events, or whether its insulation was aged.
Step 2: inspection and oil
- External check: tank deformation, leaks, and the condition of bushings and relief devices.
- Dissolved gas analysis, compared with the previous sample. An increase in arcing or overheating gases after the event is a strong signal.
- Gas in the Buchholz relay, if there is one.
Step 3: electrical tests
- Frequency response (SFRA): detects winding movement and deformation by comparison with the reference fingerprint or with sister phases.
- Leakage reactance or short-circuit impedance: changes from the nameplate or from earlier tests indicate winding displacement.
- Turns ratio and excitation current: detect shorted turns or core problems.
- Winding resistance and insulation: reveal damage to connections and insulation.
How to interpret the result
The tests are read together. If they all match the reference, it is reasonable to return to service, with closer monitoring. If one differs, it is repeated to rule out a measurement error, and the difference is investigated. If several confirm damage, an internal inspection and an evaluation with the manufacturer are advisable.
When it is not enough
Incipient mechanical damage may not show up in the tests and may only become apparent at the next event. If there is no earlier reference, comparison between phases is the fallback.
Warning: testing and re-energizing after a trip involve electrical hazards. This work must be done by qualified personnel, in accordance with applicable regulations.