What Is Evaluated in a Site Acceptance Test?

A site acceptance test verifies that the transformer arrived undamaged, was installed correctly and works as specified: inspection, electrical tests, oil tests and verification of protections and accessories.

What acceptance aims to do

The transformer has been through transport, handling, possibly storage, and assembly. The site test confirms that none of these events damaged the unit and establishes a baseline of values for future comparison. It is also the moment to document that what was received matches what was contracted.

Inspection

  • Impact records from transport and the state of the internal pressure (in units shipped with gas).
  • External damage, leaks, and the condition of bushings, radiators and accessories.
  • Comparison of the nameplate with the specification and the factory documents.
  • Ground connections of the tank and the core.

Usual electrical tests

  1. Insulation resistance and power factor or tan delta of windings and bushings.
  2. Turns ratio, polarity and vector group.
  3. Winding resistance at each tap changer position.
  4. Excitation current.
  5. Frequency response (SFRA), which serves as a reference fingerprint of the mechanical condition.
  6. Tests of internal current transformers and of core insulation.

Oil

Samples are taken for physicochemical analysis, moisture and dissolved gases. The dissolved gases taken at the outset are the reference against which any later change will be read.

Accessories and protections

  • Operation of temperature, level and pressure indicators, and of their alarm and trip contacts.
  • Buchholz relay and pressure relief devices.
  • Fans, pumps and their controls.
  • Operation of the tap changer over its full travel.

How to interpret the result

The results are compared with the factory test report, between phases and against the limits in the specification. Any deviation calls for repeating the test, investigating and resolving it with the manufacturer before energizing. The accepted data are filed as the baseline.

Warning: testing and energization involve electrical hazards. They must be carried out by qualified personnel, in accordance with applicable regulations and procedures.